The automatic meter reading program is in full swing. The program should take approximately six years to complete. The schedule for the AMR program is:
Currently the Bath, Marshall Warriner, Milestrip, Conewango, Quarry and Curtis substations are operating. Consumers on these substations DO NOT need to read their meters. All readings are being done on the 1st of each month. Meters on the Lindley and Sullivan Road substations will begin being installed May 2008. Look for future updates as more accurate information becomes available. If you have any questions, please call Cindy Hayes, Member Services Manager at 1-800-843-3414 or email at chayes@steubenrec.com.
|